E Main St Construction Work Schedule

Work began on E Main St between Rouse Ave and Church Ave on Monday, June 5, and will continue as listed below:
  1. June 5 - July 5: E Main Rouse to Church
  2. June 19 - August 1: Church from Main to Babcock, and Babcock from Rouse to Church
  3. August 7 - August 21: N Bozeman from Main to Mendenhall
  4. August 21 - September 21: E Main from Bozeman to Rouse
All DTNBZN and Community Events will operate a planned and construction will halt or be redirected during these times.